What Is RIBA Work Stage 1? A Guide to Project Preparation and Project Briefing

What Is RIBA Work Stage 1?
A Guide to Project Preparation and Project Briefing

Understanding the second stage of the RIBA Plan of Work and how careful preparation establishes the foundations for a successful architectural project.

02 NOVEMBER 2026 | RIBA WORK STAGES

 

A GUIDE TO PROJECT PREPARATION AND PROJECT BRIEFING

Understanding the second stage of the RIBA Plan of Work and how careful preparation establishes the foundations for a successful architectural project.

Whether you are planning a house extension, renovating an existing property, designing a new-build home or developing a commercial building, understanding the architectural process can help you make informed decisions before construction begins.

At Architecture North Ltd, we follow the RIBA Plan of Work, a structured framework developed by the Royal Institute of British Architects to guide building projects from their earliest stages through to completion and use.

RIBA Work Stage 1, known as Preparation and Briefing, is where the project begins to take shape. Following the initial strategic decisions made during RIBA Work Stage 0, Stage 1 focuses on developing the client’s requirements into a clear, achievable and coordinated Project Brief.

 

WHAT IS RIBA WORK STAGE 1?

 

RIBA Work Stage 1 is the Preparation and Briefing stage of the architectural process.

Its purpose is to establish a clear understanding of what the project needs to achieve, how it might be delivered and which requirements must be considered before design proposals are developed.

Rather than immediately producing detailed architectural drawings, this stage concentrates on gathering information, assessing feasibility and defining the Project Brief.

The process can involve reviewing the existing building or site, identifying the client's accommodation requirements, considering project budgets and establishing the initial programme.

The principal outcome is a sufficiently developed Project Brief, supported by the information and early feasibility work needed to inform RIBA Work Stage 2.

 

WHY IS PREPARATION AND BRIEFING IMPORTANT?

A successful architectural project relies on much more than an attractive design. Before architectural drawings are developed, it is essential to understand the client's objectives, existing site conditions, available budget and practical considerations that may influence the proposed development.

RIBA Work Stage 1 – Preparation and Briefing establishes the foundations for a successful project. It allows the architect and client to define their requirements, assess the site's opportunities and constraints, consider planning and regulatory matters, and establish realistic expectations for the design process.

Whether you are planning a house extension, property renovation, new-build home or commercial development, effective preparation helps identify potential challenges before substantial design work begins.

By developing a clear Project Brief, considering indicative costs and timescales, and identifying any additional surveys or specialist consultants required, this stage helps reduce the risk of unnecessary redesign, unexpected professional fees, construction costs and project delays.

Ultimately, RIBA Work Stage 1 provides a coordinated foundation for RIBA Work Stage 2 – Concept Design, helping ensure that architectural proposals are informed, achievable and aligned with your objectives.

KEY ACTIVITIES IN RIBA WORK STAGE 1

CLIENT CONSULTATION
& REQUIREMENTS

PROJECT SITE APPRAISAL

MEASURED SURVEYS
& EXISTING DRAWINGS

INDICATIVE PLANNING
AND REGULATORY REVIEW

DEVELOPING YOUR
PROJECT BRIEF

INITIAL BUDGET
& PROGRAMME

SUSTAINABILITY
OBJECTIVES

CONSULTANT
REQUIREMENTS

RIBA STAGE 0 vs STAGE 1:
WHAT IS THE DIFFERENCE?

Although the two stages are closely connected, they serve different purposes.

Stage 0 considers the underlying need for the project and whether a construction project is the appropriate response. Stage 1 develops the selected project direction into a clearer set of requirements and establishes the information needed to begin design.

RIBA WORK STAGE 0
STRATEGIC DEFINITION

Stage 0 considers the underlying need for the project and whether a construction project is the appropriate response.

It may involve assessing strategic options, business requirements, existing assets and potential alternatives.

The central question is:

What is the best way to achieve the client's objectives?

RIBA WORK STAGE 1
PROJECT PREPARATION AND PROJECT BRIEFING

Stage 1 develops the selected project direction into a clearer set of requirements and establishes the information needed to begin design.

The central question becomes:

What does the proposed project need to achieve, and what information is required to design it successfully?

In simple terms, Stage 0 establishes the strategic direction, while Stage 1 prepares the project for architectural design.

WHAT HAPPENS AFTER RIBA WORK STAGE 1?

Once the Project Brief has been sufficiently developed and the client is ready to proceed, the project moves into RIBA Work Stage 2 – Concept Design.

During Stage 2, the architectural team begins exploring design proposals that respond to the agreed brief.

Depending on the project, this may involve:

  • Developing initial architectural layouts.

  • Exploring building form and massing.

  • Considering spatial relationships.

  • Reviewing materials and architectural character.

  • Developing the design in response to planning constraints.

  • Coordinating early technical and sustainability considerations.

  • Reviewing the emerging design against the budget.

Stage 1 provides the information and direction needed to undertake these activities effectively.

A well-prepared Project Brief helps the architect evaluate design options against the client's established requirements.